The slab is down and the curing has begun. It is not laser flat – 1/8″ – 1/4″ variance in couple spots in the field, but the pad is smooth. I had the apron poured extra thick (8-9″) brush finished and control joints troweled in. I had a sprinkler on it for the 1st 24 hours and soaker hoses and a poly/burlap wrap was applied just after the slab control joints are cut yesterday morning.
I will let is cure for another 5 days and then apply a densifyer (Ashford) on top. Framing will start next Thursday or Friday. I am so exited that I feel like a pimply teen who just scored a playmate as a prom date!